July 25, 2025
The weather has been great in North Wales and within a week the build has cleared the site and compacted the first stage, the photo doesn’t do it justice but it’s coming along quickly and these lads really know what they are doing , it is going to be a phenomenal asset for the town.
Regards Andrew Wood
June 2025
The weather has been kind allowing progress to be made:
-All the land drains are done
-All the silt traps in position
-Track , tarmac and tree route protection is in place
-Topsoil has been harvested and put for reuse on on side
-Heras fencing relocated to boundary area
-Gorsedd stones area marked out for protection
-Signage for track and health and safety site in place
-Main work team in on Monday and 800 tonnes of recycled crushed to come over the next week for the foundation
-Shrubs and fencing orders sources under way
-Welfare unit for workers installed and access road fenced off
-Will up date next week
Regards Andrew Wood